Tepco’s Reactors May Take 30 Years, $12 Billion to Scrap - Bloomberg

Damaged reactors at the crippled Fukushima Dai-Ichi nuclear plant may take three decades to decommission and cost operator Tokyo Electric Power Co. more than 1 trillion yen ($12 billion), engineers and analysts said.

Four of the plant’s six reactors became useless when sea water was used to cool them after the March 11 earthquake and tsunami knocked out generators running its cooling systems. The reactors need to be decommissioned, Tepco Chairman Tsunehisa Katsumata said today. He couldn’t give a timeframe.

via www.bloomberg.com

March 31, 2011 | Permalink

TrackBack

TrackBack URL for this entry:
https://www.typepad.com/services/trackback/6a00d834553e4469e2014e6046e164970c

Listed below are links to weblogs that reference Tepco’s Reactors May Take 30 Years, $12 Billion to Scrap - Bloomberg:

Comments